This was the big day to pour concrete. Praise the Lord for sunny dry weather and 4 different subcontractors on the job site. 10 people from the concrete plant, 12 from the concrete finishing company, 1 person representing our concrete contractor, 1 person running the pump truck, and Keith, Bill, Cal and 2 other employees from Dean Ryan Homes. 29 people working to make this a safe successful pour. Again, we thank God that this could happen before the ground freezes.
 |
| First cement truck arrives; 6:30am |
 |
| Concrete pump truck |
 |
| This machine is called a Laser Screed. It automatically levels the concrete using laser electronics. |
 |
| Laser Screed. You can see the laser tripod in the background. |
 |
| The head of the laser screed pulls and vibrates the concrete to smooth. |
 |
| Leroy, Bob and Bill taking in all the action. |
 |
| More onlookers on this sunny day. |
 |
| Last of 23 trucks! |
 |
| Almost finished pouring! |
 |
| Keith takes a pose on the Ride-on power trowel...the workcrew was on these trowels till dark smoothing the floor. (This is Rob's version of the Zamboni!) |
 |
| 4 power trowels at work till dark. |
Great job on the blog Jana! It looks great and the pics are wonderful.